Happy New Year everyone! It’s been a little while since our last post, so we have a lot of updates to share. Despite the heavy rains in December, the contractor is moving ahead with the project. The Operations & Maintenance building is almost complete, with our operations team planning to move in come mid-February. Here’s a look at the new maintenance yard:
The sports courts are all well-defined now and the lights are installed. Here are two photos showing the tennis courts and new multi-use court:
The central path bisecting the new tennis courts has been paved and soon will receive the same concrete paver bands that are across the entire project:
And finally, a recent photo of the new restroom building. The orange panels are a waterproofing layer that will be hidden under the final architectural treatment.