Mission Dolores Park – Dolores Street Sidewalk Repairs

$
0
0
Mission Dolores Park – Dolores Street Sidewalk Repairs

The Mission Dolores Park contractor will be repairing the sidewalk on 18th Dolores Street between 18th and 19th Streets starting Monday September 8th. The sidewalk will be closed for about 1 week during this process.

In fact, pathways around the entire park are continuing to take form. This photo is of the new accessible path above the North Field, which will receive concrete next week:

Dolores Park ADA Path prior to concrete pour - showing rebar and edges

At 19th Street, the plaza concrete is almost complete:

Dolores Park - 19 Street Plaza, new concrete being poured & smoothed

And finally, if you were near the site last week, you will have noticed the shotcrete action at the Operations Building.  Here’s a panorama from inside the new building:
Operations building after shotcrete performed - view of interior space